FBMS 128 Manley St (Phase 1)

Project

FBMS 128 Manley St (Phase 1)

Residential: Multi-family

Brockton, MA | 2024

  • 14.3K GSF
  • 1 Company

About

This project is the adaptive re-use of the vacated, 3-acre, former Army Reserve Center at 124 Manley Street into a Housing Resource Center for Father Bill’s & MainSpring with 30 units of supportive housing. The existing site has two structures; the larger, 14,304 square foot, 1-1/2 story, uninsulated, masonry and steel structure main building and a modest brick garage out building which is not scheduled for renovations.

Phase 1 is the renovation of the existing main building into the Housing Resource Center. The structure will get a “deep energy retrofit” with a new exterior insulation and cladding, windows, roof, and HVAC systems. It will provide 128 emergency shelter beds and additional emergency overnight accommodations as needed, a full commercial style kitchen with a large dining/common area, new bathrooms, a health clinic, and offices for staff, case managers and counseling. The site and building will be made fully accessible per MAAB guidelines and a ramped walkway will be included to allow access to and from Manley Street. The site is to be improved with new lawn & trees, shrubbery, and perennials, ‘dark sky’ site lighting, existing fencing changes, and a new parking lot with bike storage and an on-site storm water collection and infiltration system. Phase 1 will have 26 parking spaces.

Is the project Net Zero Energy or Net Zero Energy Ready?

Net Zero (Targeting)

Project Size in GSF

14.3K

Category of height

Low-Rise

Number of residential units

30

How is the building all-electric for heating?

Air-source Heat Pump

Is the service hot water all-electric?

No

What is the primary system type for domestic hot water?

Fossil-fuel fired

On-site renewable energy

0%

Is the owner purchasing off-site renewable energy to offset all electricity consumption?

No

Site EUI Energy Use Intensity is the amount of energy a project uses per square foot over the course of a year. Site EUI = Annual Energy Use (kBtus) / Building(s) Area (ft²) / One Year (yr)

16.2 kBtu/sf/year

Net Site EUI

16.2 kBtu/sf/year

The EUI is

Modeled

What is the climate zone for this project?

6B Cold Dry

Project Team

Sustainability Consulting
  • West Work

    In Business Since 2020

    306.3K GSF

    9 Projects

    2 Professionals

Architecture
  • West Work

    In Business Since 2020

    306.3K GSF

    9 Projects

    2 Professionals