"CMTA provided the Zero Energy and power resiliency consulting for the Project Design Criteria package for the Joint Government Center Campus (JGCC). The initial charrette was to develop an energy goal for the project and define the cost for zero energy and potential for electrical resilience through battery storage. The energy goal of the project was set at 30 EUI (Energy Use Intensity) and is designed to be 100% electric for an operationally carbon neutral campus. Through CMTA’s workshops with the city and county, the criteria package incorporates a high-performance envelope and HVAC system that will reject heat to the Floridan aquifer. The budget was increased ~5% to incorporate funding to reduce energy consumption and add on-site renewable energy."

Project Owner

Miami-Dade County Government

Is the project Net Zero Energy or Net Zero Energy Ready?

Net Zero Ready

Project Size in GSF

1.1M

Category of height

High-Rise

How is the building all-electric for heating?

Water-source Heat Pump (e.g. lake-source, ocean-source, wastewater-source)

Is the service hot water all-electric?

Yes

What is the primary system type for domestic hot water?

Unspecified

On-site renewable energy

18%

Is the owner purchasing off-site renewable energy to offset all electricity consumption?

Yes

Site EUI Energy Use Intensity is the amount of energy a project uses per square foot over the course of a year. Site EUI = Annual Energy Use (kBtus) / Building(s) Area (ft²) / One Year (yr)

72.0 kBtu/sf/year

The EUI is

Modeled

What is the climate zone for this project?

1A Very Hot Humid

Websites for more information

Project Team

Energy / Sustainability Consulting
  • CMTA

    In Business Since 1968

    3.3M GSF

    23 Projects